Compass Mining is pleased to provide the following facility updates for October 6, 2022.
Please note the structure used below for all Compass products:
- Facility updates: updates on any facility changes, including moving miners between locations, downtime, or general information about one of Compass's partner facilities.
- Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.
- Bundle updates: information on individual bundle deployments or re-locations can be found here.
Helpful Links:
- Your Compass Dashboard for your order information.
- Compass Status page for real-time updates on facility status.
- Naming conventions for each facility here.
Facility Updates
Ontario 1: The facility is now back online. Ontario 1 clients have been emailed further communications on the rate increase and potential options for hosting. We thank you for your patience while we worked with our facility partner on a resolution.
Texas 3: MINI Bundle, Lonestar Bundle 1 & 2, VIP Bundle, R-NA Bundle and S19j Pro singles are all slated to come online at Texas 3. Compass Mining will send out email notifications to clients when a group of units from a deployment goes live.
The initial 1,500 unit deployment was brought back offline last week after the Energy Reliability Council of Texas (ERCOT) asked the site operator to wait for further administrative approval. The 5 MW of units were restored to operations yesterday evening, following approval from ERCOT.
We remain on standby for the remaining deployments, which will follow chronologically with re-deployments and bundle dates. A further 6,000 units are slated to come online after ERCOT approves the maintenance work completed in late September.
Texas 1: All units are deployed and hashing. Compass Mining is contacting any clients whose units are not online at this time due to machine errors.
Our finance team is issuing downtime credits for all offline hours experienced at Texas 1, beginning at the end of June.
Georgia 2 &3: The relocation of units from Georgia 2 and Georgia 3 is underway, with 33% of the units back online at Texas 1.
The following 33% of units are online, with a further 33% coming online this Friday, October 7 and the last batch Friday, October 14.
Please note that weather conditions caused by Hurricane Ian have postponed shipment of some miners from Georgia 2 & 3 to Texas 1.
Indiana 2: The Indiana 2 site is currently operational, with rolling deployments from multiple re-locations.
- S19 series units from Pennsylvania are online and hashing at Indiana 2. A few remaining units are being brought online this week.
- S19 series units from Maine 1 are online and hashing at Indiana 2. A few remaining units are being brought online this week.
- New Mexico units have begun redeployment to Indiana 2 following routine maintenance and servicing. The first batch of units are in transit. Units are expected to go back online by mid-to-late October.
- Clients who opted for Unit 1 of their XP Bundles and August Singles to be deployed in Indiana 2 are now online. Please check your Compass email and respond to our request for site selection if you have not already.
Florida 1: Florida 1 hosts both Antminer Z15 units and Antminer S19 units.
- Maine Antminer Z15 units are deployed in Florida 1. All units are expected to go online by the beginning of next week. Currently over 200 units are racked and hashing.
- Some S19 units were identified during machine review for needed maintenance. All miners have been contacted by email for expected repair and redeployment status.
Oklahoma 3: Compass Mining removed 170 units from the Oklahoma 3 facility, after the facility partner encountered an electrical component failure.
These units are being redeployed to Indiana 2 and are currently in transit, after maintenance and servicing. The units are currently packaged and ready for shipment to Indiana 2. We now expect redeployment and hashing to commence by Monday, October 17.
Manitoba 8: This site is on-track for late October deployments.
Newfoundland and Labrador 1: Units have arrived on-site and have begun hashing as of Friday, September 16.
Deployment Updates
S19J Pro 100 July (single units), S19J Pro 100 August (single units): July and August units are currently offline and slated to go online as the site energizes and units are configured at Texas 3.
S19J Pro 100 September (single units): This deployment is ready to go online after energization and configurations are complete at Texas 3.
M30s++ August and September (single units): Units have been deployed in Minnesota for those clients that chose Minnesota hosting. Units will be deployed in Texas 3 during September. Please check the email associated with your Compass account for an email asking for your facility preference.
S19 XP 140 TH August and September (single units): S19 XP units have been deployed in Indiana 2. S19 XP units have also arrived in Texas 3 and will be deployed once the site is energized. Please check the email associated with your Compass account for an email asking for your facility preference.
The September batch of units are expected to come online after energization and configuration are complete.
Bundle Updates
Mini Bundle (MINI): The Mini Bundle deployment is ongoing. Units 1 through 4 are fully deployed.
- 15% of Unit 5 is online at Texas 3 with the remaining units ready to go live after further energization and configurations.
- Unit 6 is installed in Texas 3 and is expected to go live once energization and configurations are completed.
US VIP Bundles: The remaining units will be deployed in Texas 3. Unit 6 is now fully deployed.
- Unit 7 and Unit 8 are ready to go live once energization and configuration are complete.
- Unit 9 is expected to be deployed with an estimated online date one week after Unit 7 and 8 go online.
- Unit 10 and 11 are expected to be deployed with an estimated online date of Friday, October 21.
- Unit 12 is expected to be deployed by the original estimated online dates of Monday, Wednesday, November 30.
R-NA VIP Bundle: The remaining units will be deployed in Texas 3. Unit 5 is now fully deployed.
- Unit 6 and Unit 7 are expected to go online once the facility energizes and configures units.
- Unit 8 is expected to be deployed with an estimated online date one week after unit 6 and 7 go online.
- Unit 9 and Unit 10 are expected to be deployed with an estimated online date of Friday, October 21.
- Unit 11, and 12 are expected to be deployed by the original estimated online dates of Monday, October 31, and Wednesday, November 30.
LONE 1 Bundle: The deployment is ongoing. Unit 4 is fully deployed.
- Unit 5 is installed in Texas 3 with 50% of units now hashing. The remaining 50% will go online after the site energizes and configures units.
- Unit 6 is expected to go online once the site energizes and configures units.
LONE 2 Bundle: This is the second LONE Bundle. Unit 1 is fully deployed. Unit 2 has been deployed in Texas 1 and the remaining units will be deployed in Texas 3.
- Unit 3 and Unit 4 are expected to go online after energization and configuration.
- Unit 5 and 6 are expected to be deployed during October.
Next Generation Bundle August: For Unit 1, S19 XP units have been deployed in Indiana 2. S19 XP units have also arrived in Texas 3 and will be deployed once the site is energized. Please check the email associated with your Compass account for an email asking for your facility preference for Unit 1.
- Unit 1 - Indiana units are deployed, Texas 3 units are pending site energization and configuration.
- Unit 2 - Texas 3 units are pending site energization and configuration.
- Unit 3 - October 31
- Unit 4 - November 30
- Unit 5 - December 31
- Unit 6 - January 31
Next Generation Bundle September: This deployment is waiting for energization and configuration at Texas 3.
- Unit 1 - Texas 3 units are pending site energization and configuration.
- Unit 2 - October 31
- Unit 3 - November 30
- Unit 4 - December 31
- Unit 5 - January 31
- Unit 6 - February 28
For previous deployments, please submit a ticket via the support site: Support Ticket
We ask all clients to provide pool information before deployment by logging into the Compass Mining dashboard. You can find additional information about mining pools on the Compass Mining FAQ page.
As always, we are committed to service and support excellence. If we can answer any questions, our customer support is available 24/7 by submitting a request: Support.