We reached an overall uptime of 97.95% last week. For further details, please see the chart below:

Helpful links:

Facility Updates

🆕 Nebraska Site (NE2):

The site experienced a transformer outage soon after energization. The onsite team was forced to de-rack and re-rack approximately 800 miners to a different part of the facility to minimize downtime. This effort consumed nearly all the resources on-site, leading to some delays in diagnostics and troubleshooting. We expect the technicians to switch back to normal operations this week, so we’ll have movement on our diagnostic backlog.

Ontario 1:

Last week, we experienced no curtailments, achieving 100% uptime and increasing machine utilization to 96%. On-site technicians continued to work on hashboard repairs for the miners. Furthermore, the changes we have made to our communication channel with the facility technicians are working well and leading to improved coordination and machine utilization.

Ohio 2:

Last week, maintenance was performed to enhance the site’s performance. We are also seeing reduced temperatures in the region, which has reduced the overheating issues at the site, resulting in a slight increase in machine utilization.

Texas 1:

While there were several instances of curtailment, the site's uptime improved to 95%, and machine utilization also improved marginally. The on-site team is actively addressing the list of miners requiring troubleshooting to enhance performance further.

Texas 5:

The regular curtailments in Texas are impacting the site’s ability to maintain high machine utilization. However, the on-site team continues to work diligently through the pending action items, and we remain optimistic that site utilization will improve. 

Curtailments & Outages: 

The table below presents an overview of downtime across our facilities for the past week:

Facility

Number of Outages

Estd Start Time

Min Duration

Max Duration

Average

MB6

1

5 AM (EST)

2

2

2

OH2

1

2 AM (EST)

1

1

1

TX1

4

7 AM (EST)

1

3

2

TX5

4

7 AM (EST)

1

2

1

MN1

2

7 AM (EST)

1

5

3

IA2

2

12 PM (EST)

3

4

4

IA3

2

1 PM (EST)

2

4

3

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Facility

Miner Model

Units Available

Iowa 2

Antminer S21 XP 270TH

18

Iowa 3

Antminer S21 Pro 234TH

69

Minnesota 1

Antminer S21 195TH

115

Minnesota 1

Antminer S21 200TH

81

Ohio 2

Antminer S21 200TH

44

Ontario 

Antminer S21 188TH

120

Ontario

Antminer S21 200TH

116

Texas 1

Antminer S21 188TH

106

Texas 1

Antminer S21 195TH

95

Texas 1

Antminer S21 200TH

215

Relocation Updates

Texas 3 & Nebraska 1 Relocation

The new Nebraska 2 site is up and running, with nearly 2,300 miners hashing to customers already. We have worked around the transformer issues by re-racking the miners to a different part of the facility. A very small number of TX3/NE1 relocation miners remain at the Denver Serice Centre, which will be deployed in small batches at our other partner facilities.