Last week, our overall uptime across all sites was 97.98%. For more details, please refer to the chart below:
Helpful links:
- Your Compass Dashboard for your order information
- Compass Status page for real-time updates on facility status
- Naming conventions for each facility here
Facility Updates
Iowa 2 & 3:
The resolution of electrical issues at Site 3 depends on the arrival of the ordered parts, which are expected to arrive this week. Status Page updates will be provided accordingly.
Nebraska 2:
The recent weather improvement has had a positive effect on the facility. Minor adjustments are being implemented to ensure full operational capacity, and the team is working to integrate our newly acquired units into active operation.
Ohio 2:
The onsite electricians are working to resolve several issues. These include faulty outlets that have caused delays and power cable management problems in some containers. Bolt-on repairs, storage organization, and additional site maintenance tasks are also underway.
Texas 5:
An electrician was called to the site last week to address multiple PDU failures. The issue was resolved the same day.
Texas 6:
Exhaust fan failures are causing overheating issues at the site. Our current priority is to repair the exhaust fans and optimize operations to enhance performance. Routine electrical maintenance and testing are also in progress.
Curtailments & Outages:
The table below summarizes the downtime (including curtailment, power outages, and maintenance) at our facilities over the past week:
Deployment Updates
Please submit a ticket request if you have any questions or concerns.
We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:
Relocation Updates
Texas 3 & Nebraska 1 Relocation
The relocation of miners is almost finished, with fewer than 100 of the over 20,000 units remaining.
Texas 1 Relocation
1,300 miners still need to be redeployed over the next few weeks, although most of the Texas 1 miners have already been relocated.
Manitoba 2 & Manitoba 9 Relocation
All Manitoba 2 and Manitoba 9 units have been removed from their racks and will be relocated to a Compass facility in the United States by March 2025. Customers who have opted to swap their miner to prevent relocation will receive updates on subsequent steps via their respective support tickets.