Last week, our overall uptime across all sites was 95.76%. For more details, please refer to the chart below:

Helpful links:

Facility Updates

Iowa 2 & 3:

The site's utilization has returned to 96%. Our on-site technicians are diligently working to bring additional miners back online and are addressing the backlog of diagnostics and repairs.

Ohio 2:

Our primary focus for on-site container maintenance is bringing C4 back online. We have received approval to energize more than 350 units in one of our containers this week, and we expect additional units to come online in the upcoming weeks.

Texas 6:

The facility is still undergoing routine electrical maintenance and testing, resulting in intermittent downtime. Status Updates will be posted as new information becomes available.

Curtailments & Outages: 

The table below summarizes the downtime (including curtailment, power outages, and maintenance) at our facilities over the past week:

Facility

Number of Outages

Estd Start Time

Min Duration

Max Duration

Average

IN1

5

4 AM EST

4

4

4

IN2

5

2 AM EST

4

5

4

ON1

3

8 PM EST4

1

1

1

TX5

3

2 AM EST

1

9

6

MN1

7

1 AM EST

1

3

2

IA2

1

2 AM EST

4

4

4

IA3

1

2 AM EST

4

4

4

TX6

3

7 AM EST

1

4

2

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Miner Model

Facility

Whatsminer M50s++ 164TH

Minnesota 1

Antminer S21 188TH

Iowa 2/3, Minnesota 1, Nebraska 2, Texas 6

Antminer S21 195TH

Indiana 2, Iowa 2/3, Minnesota 1, Nebraska 2, Ohio 2, Texas 6

Antminer S21 200TH

Indiana 2, Iowa 2/3, Minnesota 1, Nebraska 2, Ohio 2, Texas 6

Antminer S21 Pro 234TH

Indiana 1/2, Iowa 3, Nebraska 2

Antminer S21 XP 270TH

Indiana 1, Iowa 2, Nebraska 2

Relocation Updates

Texas 3 & Nebraska 1 Relocation

With only 80 units left to be moved, the relocation of the over 20,000 mining units is nearing completion.

Texas 1 Relocation

Fewer than 1,000 units are awaiting to be shipped out for redeployment in the coming weeks. The majority of the Texas 1 miners have already been relocated.

Manitoba 2 & Manitoba 9 Relocation

All Manitoba 2 and Manitoba 9 units have been removed from their racks and will be relocated to a Compass facility in the United States by March 2025. Customers who have opted to swap their miner to avoid relocation will receive updates on subsequent steps via their respective support tickets.

Ontario 1

The facility has prepared 48 pallets of miners for shipment. Our on-site technicians will continue to de-rack and prepare units for relocation. Additionally, the first batch of miner swaps is now available in the customer dashboard. Customers who have not yet responded to the relocation tickets have until April 1, 2025 to inform Compass of their preferred course of action.