Compass Mining is pleased to provide the following facility updates for June 5, 2023.

Summer mining is now here! Please note that all North America-based facilities are likely to experience heat-related issues over the next few months as ambient temperatures surpass 80 degrees Fahrenheit. Follow the Compass Mining status page for site-wide updates.


Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass’s partner facilities
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations

Helpful links:

  • Your Compass Dashboard for your order information
  • Compass Status page for real-time updates on facility status
  • Naming conventions for each facility here

Facility Updates

Ohio 2: Energization was successful on Friday, with over 600 units now online. Compass Mining staff are on-site racking deployments planned for late May/early June.

Deployment Updates

Bundles:

Mini Bundle 1: Unit 6 is 99% deployed! 5 units are left in deployment.

LoneStar 2: Unit 6 is 70% deployed. Deployments will continue as units are energized in Texas 3 and Texas 5.

US-VIP: Bundle is fully deployed!

RU-VIP: Bundle is fully deployed!

Next Generation Bundle and/or S19 XP Single Orders: Remaining orders remain on standby. Unit allocations may go to alternative sites, depending on the best timeline for units to be energized.

Singles:

Antminer S19j Pro 100TH - Ohio 2 May 15 Batch: Batch is fully deployed!

Antminer S19j Pro 100TH - Ohio 2 May 25 Batch: Batch is fully deployed!

Antminer S19j Pro 100TH - Ohio 2 May 31 Batch: Batch should be deployed by the end of this week.

Antminer S19j Pro 100TH - September Batch: Batch is 83% Deployed. Deployments will continue as units are energized in Texas 3. There are 145 left to deploy.

Relocation Updates

South Carolina 2 Relocation: 1,200 units are now energized. The final batch of units are now going online this week, minus some WhatsMiners taken for cleaning. Please file a support ticket if your unit is not online by the end of this week.

Redeployed S19 XP (Former Texas 4 units): 140 units have arrived at Ohio 2 for energization.

Remaining units remain in shipment or in service queue with our partner. We continue to be in dialogue with Bitmain concerning these units.