Our facilities achieved an uptime of 96.82% last week, with some curtailments affecting performance at several locations. Please refer to the chart below for specific details:
Helpful links:
- Your Compass Dashboard for your order information
- Compass Status page for real-time updates on facility status
- Naming conventions for each facility here
Facility Updates
Ontario 1: The facility experienced several instances of curtailment due to high temperatures. Currently, onsite technicians are actively addressing an issue with a network switch that is affecting some miners.
Ohio 2: The on-site technicians are currently doing essential maintenance work in one of the containers, which is crucial for the site's ongoing expansion. A few miners are currently offline, as work on the exhaust fans in one of the containers is still pending.
Minnesota 1: Despite experiencing a power curtailment, the Minnesota facility has delivered an uptime of over 97%. Our ongoing coordination with the facility has allowed us to streamline troubleshooting actions and consistently maintain over 98% utilization at the site.
Manitoba 2-9: The facility maintained an overall uptime above 99% last week, with 95% of the miners being healthy and online for most sites.
Curtailments & Outages: Last week, Ontario and Texas 5 were the only facilities that experienced multiple curtailments. The table below outlines the downtime experienced across our facilities over the past week:
Deployment Updates
Please submit a ticket request if you have any questions or concerns.
Turnkey Miners
We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:
Future Deployments
We have no pending future deployments at this time.
Relocation Updates
Texas 3 & Nebraska 1 Relocation
Last week, we shipped approximately 1,100 units to the Indiana facility. We expect them to start coming online as the on-site racks them. More relocation units will continue to ship to other sites as rackspace becomes available. All units are expected to be relocated by the end of August.