Our facility uptime has improved and reached 96.33%, as ver the past week, the decrease in curtailments has resulted in higher uptime across all our sites.
Below, you'll find the uptime and utilization statistics for each facility:
Helpful links:
- Your Compass Dashboard for your order information
- Compass Status page for real-time updates on facility status
- Naming conventions for each facility here
Facility Updates
Indiana 1/2: Indiana facilities have consistently maintained 100% uptime in the past few weeks, and we are also seeing a noticeable increase in utilization.
Iowa 3: As part of our expansion in Iowa, an additional 3000 slots will come online over the next two weeks. 90% of these slots will be dedicated to Texas 3 relocation.
Ontario 1: Last week, the technicians continued working through the diagnostics and repair queue to achieve optimal site performance while addressing breaker issues on a few racks. A portion of the site is affected by overheating, and the technicians are working diligently to mitigate the problem.
Ohio 2: Some containers are still out of service due to electrical issues, and we are emphasizing the need for the site operator to resolve these issues swiftly. We will update the status page as soon as we have more information.
Texas 5: The team performed maintenance on one of the transformers, which resulted in a brief outage for a portion of the site. Additionally, technicians are working through the diagnostics and repair queue to enhance the site’s utilization and uptime. The site utilization is ranging between 92-95% and on the uptrend.
Curtailments & Outages:
We are pleased to report minimal incidents and major outages across all our facilities. The table below provides a summary of downtime for the past week.
Deployment Updates
Please submit a ticket request if you have any questions or concerns.
Turnkey Miners
We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:
Relocation Updates
Texas 3 & Nebraska 1 Relocation
The cleaning and inspection of the relocation units at DSC is in progress. Approximately 1100 units have been redeployed in Indiana and are hashing optimally. A batch of 850 units are en route to our facility in Iowa and are expected to be operational within the next 7-10 days. Another batch of 1600 units will also be dispatched to Iowa this week to occupy the remaining slots. The remaining relocation units will be relocated to our new site in Nebraska starting on August 15.