Compass Mining is pleased to provide the following facility updates for August 20, 2022.
We'd like to remind customers to dig back into their email inbox to find our "2022 Mining Operations Summer Update." It's full of helpful tips and tricks about mining during the summer months and what to expect with Compass Mining!
Please note the structure used below for all Compass products:
- Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.
- Facility updates: updates on any facility changes, including moving miners between locations, downtime, or general information about one of Compass's partner facilities.
- Bundle updates: information on individual bundle deployments or re-locations can be found here.
As a note, Compass shows units between both locations and bundles. Please check your Compass Dashboard if you are unsure about your purchase. Please also utilize our Compass Status page for real-time updates on facility status!
Texas 1 and Texas 3 Facility Updates
Texas 1: The Texas 1 site is now re-energized as of the last 48 hours. The first set of Compass customer units is expected to be hashing by August 23, and the remainder of the units will be hashing over the following weeks. This is a large facility with more than 100 MW of miners being deployed so the miners are coming online in phases, and Compass Leadership is working with the facility to ensure customer units are being deployed as quickly as possible.
Texas 3: Compass Leadership completed a site visit last week. ASICs are continuing to be installed with more than 10,000 Compass customer ASICs on site. Relocated miners will have first priority and all other units will be deployed chronologically based on the original order date.
Completion of construction is on schedule with the Modular Data Center units, pad mount transformers, and substations ready to go live. Commissioning-ready activities concluded late last week, which means the site is ready to energize.
Site energization involves tight coordination with the site’s power provider. Due to extreme heat conditions in the region currently stressing the grid, the site’s power provider must carefully time the final testing to minimize risk to the grid, and the communities it powers. Based on current conversations with the power provider, it is anticipated this final step to be completed by early to mid-September, rather than the last week of August which was previously communicated.
Installation of additional ASICs will continue over the next two weeks while the facility team works with the power provider.
Read: Compass Mining Announces 75MW Site Expansion With Compute North
Facility Updates
Minnesota: M30S++ units for both August and September batches are being installed. ASICs have already started hashing to pool accounts and the deployment is ongoing.
Indiana 2: Compass has secured additional capacity with the Indiana partner at a new site Indiana 2. This facility is ready now for ASICs. All relocated Pennsylvania miners will be hosted in Indiana 2. These ASICs are in transit to the facility with an estimated hashing date of August 26.
Florida: Additional capacity is now available at the Florida facility and the relocated Z15 will be deployed there. An email will be sent out next week for Z15 customers.
Deployment Updates
S19J Pro 100 TH July (single units): ASICs have already been racked at Texas 3, and pending energization in early-mid September as per the Texas 3 update above.
S19J Pro 100 TH August (single units): ASICs have already arrived onsite at Texas 3 and are currently pending installation. This batch is now expected to be energized in mid-September.
S19J Pro 100 TH September (single units): This deployment is on track for September 30.
M30s++ August and September (single units): Customers have the opportunity to remain in Texas 3 (go-live mid-September) or come online in Minnesota now. Please check your email if you haven't provided a decision already.
S19J Pro 104 TH August (single units): This deployment had an online date of August 10 and August 17 in Indiana. All units are ready now. If your units are not online, please provide your default pool information in your Compass Dashboard.
Next Generation S19XP August (single units): Customers have the opportunity to remain in Texas 3 (go-live mid-September) or come online in Indiana (expected by August 31).
Next Generation S19XP September (single units): This deployment is on track for September 30.
Bundle Updates
Unit 4 (MINI): Unit 4 was deployed across three sites: Minnesota 1 and Manitoba 6/7. Units were deployed based on the order date, customer facility selection, and the first available space. Customers were brought online by order date. The deployment is currently 98.5% complete with the remaining customers able to come online in Indiana (within 7 days) or wait for Texas 3 to come online early-mid September.
Unit 5 and Unit 6 ASICs have already arrived in Texas 3. Unit 5 is already racked and Unit 6 is pending rack installation, and both are pending energization in early-mid September as per the Texas 3 update above.
US VIP Bundles: Unit 6 is online. The remaining units will be deployed in Texas 3.
Unit 7 and Unit 8 ASICs have already arrived in Texas 3. Both Unit 7 and Unit 8 are pending install, and both are pending energization in early-mid September as per the Texas 3 update above.
Unit 9 is expected to be energized in mid-late September. Unit 10, 11, and 12 are expected to be deployed by the original estimated online dates of September 30, October 31, and November 30.
R-NA VIP Bundle: Unit 5 is online. The remaining units will be deployed in Texas 3.
Unit 6, Unit 7 and Unit 8 ASICs have already arrived in Texas 3. Unit 6 is already racked and both Unit 7 and Unit 8 are pending rack install, and all are pending energization in early-mid September as per the Texas 3 update above.
Unit 9 is expected to be energized in mid-late September. Unit 10, 11, and 12 are expected to be deployed by the original estimated online dates of September 30, October 31, and November 30.
LONE 1: Unit 4 has been deployed, but remains offline until the Texas 1 facility provider energizes the sections of the facility where these are located. As per the Texas 1 update above, we are expecting some of the units hashing again on August 23 and the remainder over the following weeks. The remaining units will be deployed in Texas 3.
Unit 5 and Unit 6 ASICs have already arrived in Texas 3. Unit 5 is already racked and Unit 6 is pending rack install, and both are pending energization in early-mid September as per the Texas 3 update above.
LONE 2 Bundle: This is the second LONE Bundle. Unit 1 is fully deployed. The remaining units will be deployed in Texas 3.
Unit 2 and Unit 3 ASICs have already arrived in Texas 3. Unit 2 is already racked and Unit 3 is pending rack install, and both are pending energization in early-mid September as per the Texas 3 update above. Unit 4 and 5 are expected to be hashing by September 30, and Unit 6 for October 31.
Next Generation Bundle 1: Unit 1 will be deployed in Indiana and Texas 3. Customers have the opportunity to remain in Texas 3 (go-live mid-September) or come online in Indiana (expected by August 31).
The estimated deployment dates for the remaining units are Unit 2 (September 30), Unit 3 (October 31), Unit 4 (November 30), Unit 5 (December 31), Unit 6 (January 31).
Next Generation Bundle 2: Texas 3, and all units are currently on track to meet the estimated deployment dates. Unit 1 (September 30), Unit 2 (October 31), Unit 3 (November 30), Unit 4 (December 31), Unit 5 (January 31), Unit 6 (February 28).
For previous deployments, please submit a ticket via the support site: Support Ticket.
If you don't see your ASIC online, please include the Facility, Pool Info, and Reservation ID in your request.
If you would like to take custody of your undeployed bundle unit and it's passed the estimated online date, please submit a Support Ticket with your request.
As always, we are committed to service and support excellence. If we can answer any questions, our customer support is available 24/7:
Phone: +1 (888) 871-3071
Submit a request: Support