Compass Mining is pleased to provide the following facility updates for April 3, 2023

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass's partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Texas 3: Oklahoma 2 redeployments, MINI Bundle Unit 5 & 6, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units, M30S++ and S19j Pro singles are all slated to come online at Texas 3.

The remaining 7 MW of allocations have still not deployed.

The Compass Mining team is on-site along with an official Bitmain repair partner to diagnose and service any units offline. If your unit has been having issues hashing, please file a ticket and/or approve repairs if so chosen.

Texas 4: About 500 units were impacted by needed repairs at Texas 4, including about 300 S19 XPs. About 300 repairs are now done.

Bitmain’s official repair partner has paused repairs for S19 XPs pending guidance from Bitmain on these units. We ask clients to refer to our recent email communication about S19 XPs for further information, or file a ticket to get the information if you were accidentally not informed of the challenges.

We also published a report on S19 XPs with further information on the repair issue.

Manitoba 1: Some units are now back online after removal from Manitoba 1 to other sites. The remaining units are expected online by the end of this week.

Please note a subset may be sent back to the Compass Mining Service Center for repair and/or further diagnostics.

South Carolina 2: Units are now offline and are prepping for servicing and shipment. We remain on schedule for redeployment in late April.

Deployment Updates

Mini Bundle 1: Mini Bundle Unit 5 is complete minus a small minority of 3 units soon to come online at Texas 3. Unit 6 deployment is 53% complete and will continue as containers are energized in Texas 3.

LoneStar 1: Unit 6 is 99% deployed with the remaining few customers awaiting the correct model type.

LoneStar 2: Unit 5 is 97% deployed with the remaining 3% awaiting for the correct model type. Unit 6 is in queue for deployment following Mini Bundle 1 U6.

US-VIP: Unit 7 and 9 have been deployed in Texas 3. Clients were offered a free upgrade for Unit 8 to an S19J Pro 92TH for all clients who agree to hosting in Texas 4. Units 10 is 91% deployed, and 11-12 will be deployed in Texas 3 once additional containers are energized.

RU-VIP: Unit 8 has been deployed in Texas 3. Unit 10 is now 70% deployed. Units 10-12 will be deployed in Texas 3 once additional containers are energized.

Next Generation Bundle and/or S19 XP Single Orders: Units are in queue for deployment in Texas 3. Please file a support request if you’d like to go online earlier at Ontario 1 or a Manitoba site with your Next Generation Bundle and/or S19 XP Single Order at a hosting rate of $0.079. We continue to wait on additional hosting capacity at Texas 3 to place these units online.

KA3: All December and January and some February orders of KA 3 are online at Ontario 1. We continue to wait for units with a March online date to be delivered from Bitmain.

We are seeing higher failure rates (dead on arrival) units once deployed to the facilities. We are working with the facilities to hard reboot these units or send them back to Bitmain for replacement if necessary. You will be contacted individually if an issue arises with your unit.

We have Bitmain staff onsite to help troubleshoot units going online.

L7: Some January L7’s online dates are now online. A few are needing servicing after being found defective from the manufacturer. Please expect a ticket from our team if your unit was affected. All February and later online dates for L7s are awaiting word from Bitmain for delivery.

We have Bitmain staff onsite to help troubleshoot units going online.

We have received the next batch of units from Bitmain and are beginning to ship them from Hong Kong.

Texas 4 S19j Pro 100: Batch is 80% deployed. Remaining units will be deployed once energized.

Ontario S19j Pro 100: Customers were assigned temps, worker names starting with "ttx". These units will hash to customers until their permanent unit is available. Email communications will be received for both the temp assignment and the permanent unit assignment.