Compass Mining is pleased to provide the following facility updates for September 20, 2022.

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime, or general information about one of Compass's partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.
  • Bundle updates: information on individual bundle deployments or re-locations can be found here.

As a note, Compass shows units between both locations and bundles. Please check your Compass Dashboard if you are unsure about your purchase. Please also utilize our Compass Status page for real-time updates on facility status! Also be sure to check out our naming conventions for each facility here.

Facility Updates

Texas 3 Deployment Update: Our Texas 3 facility partner has informed Compass Mining that an issue with the first substation identified during Friday’s energization has pushed back Circuit 1 energization until Wednesday, September 21. We tentatively now expect units to go online on Friday, September 23.

Compass Mining will continue to push updates to clients from the facility partner as we receive information.

Over 15,000 Compass Mining client ASICs are on-site and installed, awaiting energization. Due to the large number of units, the entire deployment will take a number of weeks. The two substations supporting the site further break into Circuits 1-3 and the Circuits 4-6.

Relocated miners will have first priority and all other units will be deployed chronologically based on the original order date. Installation of additional ASICs will continue over the next few weeks until the full capacity is installed.

Read: Compass Mining Announces 75MW Site Expansion With Compute North

Texas 1: Over 95%+ of previously deployed units are now back online. The Compass team is now troubleshooting individual units.

Georgia 2 &3: The relocation of units from Georgia 2 and Georgia 3 is underway, and the first group of units will depart Georgia by the end of this week. The online target remains Friday, September 30 for the first units to go back online at Texas 1.

Indiana 2: The Indiana 2 site is currently operational, with rolling deployments from multiple re-locations.

  • S19 series units from Pennsylvania are online and hashing at Indiana 2. A few remaining units are being brought online this week.
  • S19 series units from Maine 1 are online and hashing at Indiana 2. A few remaining units are being brought online this week.
  • Some former New Mexico units are at our Denver, Colorado repair hub awaiting shipping and re-deployment to Indiana 2. Units are expected to go back online by late-September or early October.
  • Clients who opted for Unit 1 of their XP Bundles and August Singles to be deployed in Indiana 2 are now online. Please check your Compass email and respond to our request for site selection if you have not already.

Minnesota: M30S++ units for both August and September batches have been installed. ASICs have already started hashing to pool accounts and the deployment is ongoing. Please check your Compass email and respond to our request for site selection if you have not already

Minnesota 1

Florida: Maine Antminer Z15 units have started deployed to Florida 1. All units are expected to go online by mid-to-late September. Currently over 200 units are racked and hashing.

We ask all Z15 miners currently using Braiins Pool (formerly Slush Pool) to transfer to another pool service, as the Zcash pool has been deprecated. An email will be sent to all Z15 miners with information for changing pool accounts.

Oklahoma 3: Compass Mining removed 170 units from the Oklahoma 3 facility, after the facility partner encountered an electrical component failure.

Since the timeline to re-energize is unknown–as backorders for industrial level electrical equipment remain elongated–Compass Mining has decided to remove units to our Indiana 2 partner facility. The units are currently going through our Denver, Colorado repair hub. Units are expected to be online at Indiana 2 by Monday, September 26.

Manitoba 8: The site is on track to be operational by Monday, September 26.

Newfoundland and Labrador 1: Units have arrived at the site and are in the process of being racked and re-installed.

Deployment Updates

S19J Pro 100 July (single units, S19J Pro 100 August (single units): These deployments will commence once the Texas 3 containers and miners are energized. As per the Texas 3 update above, units are expected to start coming online by the end of this week.

S19J Pro 100 September (single units): This deployment is on track for Friday, September 30.

M30s++ August and September (single units): Units have been deployed in Minnesota for those clients that chose Minnesota hosting. Units will be deployed in Texas 3 during September. Please check the email associated with your Compass account for an email asking for your facility preference.

S19 XP 140 TH August and September (single units): S19 XP units have been deployed in Indiana 2. S19 XP units have also arrived in Texas 3 and will be deployed once the site is energized. Please check the email associated with your Compass account for an email asking for your facility preference.

The September batch of units are expected to come online by Friday, September 30. The majority of the September batch have arrived onsite in Texas, pending installation.

Bundle Updates

Mini Bundle (MINI): The Mini Bundle deployment is ongoing. Units 1 through 4 are fully deployed.

  • Unit 5 is installed in Texas 3 and is pending energization this week.
  • Unit 6 is installed in Texas 3 and is expected to go online by Friday, September 30.

US VIP Bundles: The remaining units will be deployed in Texas 3. Unit 6 is now fully deployed.

  • Unit 7 is expected to be deployed by Wednesday, September 28.
  • Unit 8  is expected to be deployed with an estimated online date of Friday, September 30.
  • Unit 9  is expected to be deployed with an estimated online date of Friday, October 7.
  • Unit 10 and 11 are expected to be deployed with an estimated online date of Friday, October 14.
  • Unit 12 is expected to be deployed by the original estimated online date of Wednesday, November 30.

R-NA VIP Bundle: The remaining units will be deployed in Texas 3. Unit 5 is now fully deployed.

  • Unit 6 is expected to be deployed with an estimated online date of Friday, September 23.
  • Unit 7 is expected to be deployed with an estimated online date of Friday, September 30.
  • Unit 8  is expected to be deployed with an estimated online date of Friday, October 7.
  • Unit 9 and Unit 10 are expected to be deployed with an estimated online date of Friday, October 14.
  • Unit 11, and 12 are expected to be deployed by the original estimated online dates of Monday, October 31, and Wednesday, November 30.

LONE 1 Bundle: The deployment is ongoing. Unit 4 is fully deployed.

  • Unit 5 is installed in Texas 3 and is pending energization.
  • Unit 6 is installed in Texas 3. We now expect energization for this unit by Friday, September 30.

LONE 2 Bundle: This is the second LONE Bundle. Unit 1 is fully deployed. Unit 2 has been deployed in Texas 1 and the remaining units will be deployed in Texas 3.

  • Unit 3 is deployed and pending energization.
  • Unit 4 is expected to be deployed with an estimated online date of Friday, September 30.
  • Unit 5 and 6 are expected to be deployed during October.

Next Generation Bundle August: For Unit 1, S19 XP units have been deployed in Indiana 2. S19 XP units have also arrived in Texas 3 and will be deployed once the site is energized. Please check the email associated with your Compass account for an email asking for your facility preference for Unit 1.

  • Unit 1 - Indiana units are deployed, Texas 3 units are pending site energization.
  • Unit 2 - September 30
  • Unit 3 - October 31
  • Unit 4 - November 30
  • Unit 5 - December 31
  • Unit 6 - January 31

Next Generation Bundle September: This batch is currently on track and September units will be deployed in Texas.

  • Unit 1 - September 30
  • Unit 2 - October 31
  • Unit 3 - November 30
  • Unit 4 - December 31
  • Unit 5 - January 31
  • Unit 6 - February 28

For previous deployments, please submit a ticket via the support site: Support Ticket

We ask all clients to provide pool information before deployment by logging into the Compass Mining dashboard. You can find additional information about mining pools on the Compass Mining FAQ page.

As always, we are committed to service and support excellence. If we can answer any questions, our customer support is available 24/7 by submitting a request: Support.